Hi,
I completed a sprint early, but I want to fix the timeline to match the date I completed the sprint, if that makes sense.

but when I do, it shows this warning: 'This parent issue ends before its child issues are scheduled to complete.'
I don't know how to fix it. I cannot remove the sprint from these subtasks or change the end date of the sprint I completed.
Any ideas on how to set the deadline to today's date (25 December) while avoiding the warning?