If i activate hide done items in the view settings option, It'll hide done epics but also done tasks from other epics.
I only want to hide done epics and all their child tasks, is there any way to do it?
Hello, Good day. Instead of using hide-done items, on your board JQL query you could add status != done along with the existing JQL query. Thanks
Thank you for your answer, but how can I modify the JQL query in a JIRA - Business Project? I cannot find the option, it doesn't work as a software development project:
Hello, Good day. At the moment we don't have the option to modify the filter query on JWM project templates.
So, is there any workaround for this?