I have 2 questions:
Thanks
Naama
Hi,
1) No, this is currently not possible - all views are split up per team and per member, there is no grouping of member data across teams
2) yes - this is available in the capacity view, broken down per member:
image2015-10-18 13:51:58.png
this would show you the planned capacity for a single team member, either per sprint in case of scrum teams, or per calendar week in case of Kanban teams.