First, I an a true newbie. Agile and Jira do not really fit some of the tasks that we do and here in lies the problem. Here is a typical flow for a story, which I would define as subtasks.
1) Obtain the equipment Timeframe weeks.
2) Does the written procedure exist for the equipment. Timeframe days.
3) For any equipment without a procedure create one. Time frame days.
4) Test the procedure on the equipment to make sure it is correct. Timeframe days.
5) Submit procedure for approval. Time frame 9 months or more.
6) Pass on the procedures to the appropriate departments.
With our Sprints being only 2 weeks, we do not want the story to be on the books for a year.
Any ideas on how to handle this?
Thanks in advance.
Mike Virostko