Dear all,
our Confluence instance is indicating that EOL is in end of July while
https://confluence.atlassian.com/support/atlassian-support-end-of-life-policy-201851003.html
indicates end of October. Which one is true?
Thank you
Andreas
Dear all. Thank you for your answers. I found the answer here: https://community.atlassian.com/t5/Data-Center-discussions/Announcing-Confluence-9-2-as-the-next-Long-Term-Support-release/td-p/2698067#:~:text=Learn%20more%20about%20the%20LTS&text=If%20you'd%20like%20to,time%20to%20plan%20your%20upgrade.
There was a later extension of the deadline and maybe my instance did not pick it up...
That's strange! For my Confluence instance the End of Life date for Confluence version 7.19 is showing as 31-Oct-2024.
Officially the website. However, I would upgrade before the date your instance is reporting to avoid any upgrade headaches caused by a confused instance.