Hi Team,
I recently faced this scenarion in my team. Want to understand scenario where say there is a story worth 5 SP added in current sprint and at the end of the sprint team realizes that the story still needs little more time to complete. So in such cases what is best approach ? a or b ?
a. Directly move the story to next sprint and continue with the remaining and close it there
b. Split the story in current sprint and give estimate new story as per the effort and close already existing one in current sprint and keep splitted story in next sprint .
Which approach is the most recpmmended one and why ? How does it effect velocity and other metrices. In case we go with option a then how do we measure individuals effort and team's velocity for that sprint and if we go with option 2 then how do we say wheather its a apillover or not?