I have people who work 6 hours per day , and people who work 8 hours per day.
How can i configure these?
Cheers
Hi,
You can do this in Tempo. Open your timesheet, select "Tools" and "User preferences" and update your required hours.
Best regards,
-Bjarni (Tempo)
Hi Tatiane, by time tracking you mean in the Tempo Plugin?
The configuration of time traking , first of all, is in JIRA / System / Issue Features / Time Tracking.
But i use tempo plugin too, i dont know if its possible to do what i need in Tempo plugin.
Unfortunately this can't be done, sadly, because it would be a great feature. I found these two Jira Issues:
https://jira.atlassian.com/browse/JRA-9306
https://jira.atlassian.com/browse/JRA-2780
The users basically said that the hours should be by project and not a global configuration. Altough, this wasn't implemented yet.
I would recommend you to create a Jira issue for this matter because it would be a new request.
Neither can be done in the Tempo Plugin. There are two issues but in the JTMPO project:
https://studio.plugins.atlassian.com/browse/JTMPO-11
https://studio.plugins.atlassian.com/browse/JTMPO-291
These two are exactly what you are looking for.
This does not change the hours globally?
perfect. Thankxxx