in the new portfolio 2.2 the documentation says you can create a baseline by filling target dates with whatever the plan has calculated as start and end dates
The document says:
- Go to Scope >
and check the fields target start date and target end date so they are displayed in the scope view columns. - Create the work items that need to to be done.
- Go to the Schedule settings and select Target schedule from the drop-down menu.

- Set targets > set target dates from calculated.
I cannot find the "Targets > set target dates" mentioned step #4 anywhere and the document does not provide a screenshot of where to find that button or menu.