We have recently adopted Atlas specifically for project updates and have a question about the best practice for status changes and dates.
Our interpretation of the "Off Track" status is that the original target date is no longer achievable and has to move back.
So ideally in the project update, we'd like to set the status to Off Track for the original target date and provide a new date the team is targeting. However, the phrasing in the update shows up as "Off Track for [new date]". Making it seem like we're Off Track for the new date.
The only option I can see is leaving the original target date in and adding the new date in the comments, but it's not great as that doesn't surface on the top-level list. An alternative approach would be to:
1. Set the status to Off Track, leave the original target date in and mention the new target date in the comments
2. In next week's update, set the new target date and whether we're on track for that
The only problem with this approach is that in the top-level project list this project now shows as all green, same as projects that haven't had a date change. So we've lost visibility on the fact that this project is no longer tracking to its original timeline until you click into the individual project.
I am wondering what the intention of the status & date relationship is for Off Track updates? What is the "intended" workflow for communicating that we are off track for the original date and then start tracking towards a new target date?
Thanks