in jira align, under epics i have time/skills. here i have following
Portfolio Ask
Start / Initiation
Required Field Target Completion
for these instead of date i want to fill sprints.
@manish a those are date fields for the fixed date milestones and can not align directly to sprints. I would recommend you align those dates to the end of the sprint that you would like to use.