What is behind this auto calculation? (NEED HELP)
BELOW ARE FOR FEATURE 1
THESE ARE FOR FEATURE 2
Throughput is measured in Team Weeks, not Team Sprints. If I am understanding your question correctly, it sounds like you are expecting a throughput of one to result in the forecast completion of one Story per Sprint, but it is (correctly) showing two Stories per Sprint. I'm also assuming your Sprints are the typical two weeks long.
EDIT: After further investigation, I see what appears to be a bug. I created this issue with support: ALIGNSP-21429
Ahh, so I am not crazy? Yes, I do know that KANBAN measures in weeks, thanks. Can you give me access to the bug so that I can share with my team?
Here you go: https://support.atlassian.com/requests/ALIGNSP-21429