Hello,
For some time now it has been happening in one of our teams that there is an inconsistency in the number of story points committed when I look at the velocity graph versus the number of story points that appear when I consult the sprint details. I'll post a couple of images to give you an idea, one is from the velocity chart and the other is from the burndown chart of a specific sprint. For both images I have highlighted the committed story points and it can be seen that for the same sprint in the velocity chart approximately 240 story points appear while in the burndown report approximately 90 story points appear. Would you know what could be causing this difference between both reports?
Thanks in advance!