Need a Solution !!!!!!!!!!!
In Jira I created tasks and gave estimation of 1 week . I created 2 subtasks logged work of 2 days in 1 of the sub-task.
The problem is the logged work of 2 days did not get subtracted from the task rather the estimated and remaining time in task was still 1 week and logged time was 2 days.
Can anybody help me how to apply the logic of subtracting the sub-tasks logged work with remaining time of task?