Due Date has always been optional on project, it was to allow users to update if request was long dated. There is little to no automation on project, especially nothing is in place concerning a due date. Time to resolution SLA is 2 business days; in settings, under time to resolution SLA, the Goal is 2 days. Recently the due date started populating 6-7 days from created date OR not populate at all. I thought the SLA was driving the due date but the Time to Resolution clock is still tracking items correctly. Any thoughts on what could be causing this? Am I supposed to have automation for the due date? How was it populating without automation?