Try this...
project = ABC AND component = XYZ AND type = "Program Epic" AND (("Date Planned Start" >= "2023/09/01" AND Date Planned Start" <= "2023/12/31") OR ("Date Planned Finish" >= "2023/09/01" AND "Date Planned Finish" < "2024/01/01"))
I think I have it right. I am wondering if you need the "finish" bit at all though. Maybe you have work that started in say Q3 that continues to Q4 as an example.
At a glance that seems to be working ... thanks!
Please consider accepting answer once you are confident it works.
It looks like you're new here. Sign in or register to get started.