Scenario: Developers are working on Projects, but also are Production Support. As such, they will need to be able to work on maintenance tickets. We have decided they will have 60% project work and up to 30% maintenance.
Issue: We would like to have a "bucket" in each sprint for Maintenance Tasks. Because these tasks may not be known at the beginning of the sprint (we never plan when our applications will break), we can't plan for the tasks themselves. We would like to be able to account for the 30% in a generic "MX Work" bucket that the actual tasks can be added to.
Is there a way to do that in Jira? Should we have parallel sprints, with one being the MX sprint working off the same backlog?
The object is to not skew our reporting too much because we do plan for a portion of the sprint to be for maintenance.