Hey,
do you know any option to show estimation in weeks instead of days in Advanced Roadmaps?
thank you
Michał
Hello @Michał ,
Welcome to the community !
I see you are looking for assistance in changing the estimation from Day to week. I noticed that a similar query has been answered here.
Please consider going through it and let us know if you have any followup queries.
Hope it would help you.
Have a great day ahead!
Hey @Himanshi,
thanks for answer, could you please share link once again? It doesn't work.
thanks
Apologies for keeping you awaited.
Here is the link of the community: https://community.atlassian.com/t5/Advanced-Roadmaps-questions/Show-calender-weeks-in-Jira-advanced-roadmap/qaq-p/1739033
Please try to access and let me know if it works.
thanks for reply.
Thread you mentioned is about timeline and it's values on it.
Need my project came with is unit of estimation. That is shown in advanced roadmaps fields columns.
You can choose between:
Story points
Hours
Days
So question is if weeks could be also applied as estimation units ?
Hi @Michał
Unfortunately Advanced Roadmaps doesn't support using Weeks as an estimation unit - only Hours or Days are supported for time based estimation. I believe the reasoning for this is that in the agile methodology a task that will take multiple weeks would typically be broken down into smaller tasks.
Sorry that I can't give you a better answer here, but if you'd like to request this as a feature the best option would be either through the "Give Feedback" button in the header of your plan or by raising a feature request at jira.atlassian.com.
Cheers,
Daniel