Hi, I have a structure with the hierarchy initiative - epic - story.
One one initiative, the total of story points is 460, and for one epic all stories are complete with a total of 32 story points.
I have structure with a formula column with progress based on story points, where status "Closed" counts as 100%, all others as 0%. The epic with the closed stories is correctly shown as 100%, all others as 0%.
However, the progress on epic level is 3%, but 32 divided by 460 should result in 7%.
I checked the progress calculations on epic level, they are correct, but there seems to be a problem on initiative level.