Hi Community,
I have seen my 1st project sprint into my 2nd project backlog.
How to resolve the issue. screenshot mentioned below.
The filter for the board needs to be configured to just show the issues from second project
Filter query will need to be something like project = APN AND issue type = All
although you may also want to limit which issue types are displayed also
Ok, thanks jason!!!
Will try.
Pls. check if any sprint candidate is not accidentally mapped to non-required sprint and in different project.
This usually happens in two occasions:
1. When the Board Filter is not correctly configured. In that case, you can check in Board Settings -> General -> Filter Query
2. Other scenario is that, if the first Project Jira Issues are tracked with the Sprint belonging to Second Project or vice versa.
Validate the same.
Yes, to give a more specific example, if an issue was in Project ABC and included in Sprint ABC, and then it's decided to move the issue to Project DEF, the issue will remain in Sprint ABC unless it's explicitly removed. People generally assume moving the issue will move it out of the sprint as well.
Hi,
A couple of other things to look out for, aside from the board filter, as others have mentioned:
Hope that helps, let us know if your issue was resolved