I want to retrieve all the date changes that happened to tickets in a project in custom fields.
For example, we have couple of custom date fields (Dev Planned Start Date, Dev Actual Start Date) and Dev Actual Start Date gets changed multiple times due to some blocks or issue, it was May 1 then got postponed to May 10, further to May 24.
JIRA only displays the last date (i.e May 24) but I want to see all the dates and show them in Advanced Roadmap Plan or some kind of report so that management can see how much times dates have been changed along with the dates.
Can anyone help me in achieving this?
Thanks in advance.
Surbhi