Hi guys,
I may be missing something very basic (apologies in advance if I am) but I have a question about resource allocation in Tempo Planner when it comes to over-allocation (getting a yellow line in the Planning time-line).
Three images attached. All test data.
Alex has been assigned to this project for 50%. (image 1)
I then assign two stories to Alex for the same time period (Images 2 and 3). Both assignments are 50% (3.5 hours per day). This suggests that Alex is working 7h on this project during this time. But his allocation to this project is 50% (3.5 hours).
Question: why doesn't Tempo Planner show Alex as over-allocated during this time period?
Regards,
Lee
Screen Shot 2014-11-25 at 12.26.14.png