I am trying to run a query for all issues (standard issue types) by version and get the estimated time and logged work (time spent). We record our estimates & log work on sub-tasks, however the version is often blank on these subtasks.
When I view the issue level (not sub-task), I can see the estimates and logged work rolls up to the issue like we want to see it. But when I run a query for these issues with version as my parameter, it excludes any estimates and logged work on sub-tasks where the version is empty. This makes our estimates and actuals look completely off.
How can I run a query for at the issue level (standard issue types) for a specific version but include estimates and logged work from all sub-tasks even if the version is blank?