Hi Community,
I'm a new-be in Jira and our Team has the following issue: We have a scrum board with TO DO - IN PROGRESS - READY FOR TEST - DONE
In the Done column we move all tickets which are closed or ready for release. Problem: sometimes a peson forgets to release the story and if we close the sprint and move on with the new sprint this ticket with the status "ready for release" is out of the backlog, therefore out of sight.
I suggested to do a new column: READY FOR TEST -> READY FOR RELEASE -> DONE
But also in this case my team is worried that after the sprint is done & closed those tickets "ready for release" will be vanished from the backlog.
How can we solve this issue? we want to keep the ready for release tickets in the backlog to finish them in the next sprint and dont forget them
THANK YOU