Is there a way to visualize Jira issue dependencies when the issues do not have defined start/end dates/times?
The plan view in Jira is mostly for project management. It has a gnatt chart which shows you timeline view of your tasks. So you can say when tasks start/end and it will visualize that on a gnatt chart.
This type of view is great for project management planning where it is well known when tasks are expected to be completed by.
But say you have tasks that don't have dictated start/end dates and they only have dependency:
- Tasks: A, B, C, D, and E
- B can't start till A is done
- C can't start till B is done
- D can't start till A is done
- E can't start till C and D are done
With that information in each of the Jira issues for A, B, C, and D, how can I generate a visualization like this: