For some reason, I can't display epics in a plan/schedule based on a Kanban board.
Only tasks/initiative show up but not epics despite of the hierarchy filter.
It should be like shown here.
https://community.atlassian.com/t5/Jira-questions/ability-to-drag-and-drop-move-tasks-stories-to-different-epics/qaq-p/1501089?lightbox-message-images-1501089=113362i39E95F10A06C9AF4
Any ideas which settings to check?
HI @Tamara
Are Epics displayed in the board ? Also if you run the search of the filter use to configure the board, do you see the Epics ?
Regards
Thanks, Florian, for the quick hint!
Indeed our board filter does not include epics/intiatives.
Therefore I have changed the following:
1. Create a simple new filter like "type in (initiative, Epic, task)"
2. Set this filter as the only source for the plan.
3. Reload the plan
4. Unfortunately same effect.
As you can see in the attached screenshot, initiatives do not have the expand option, and the initiative No. 6 has two associated epics for example.
What the hiearchy defined looks like in the configuration ?
Did you set the initative as Parent Link in the Epic ?
Also can you remove the group by assignee ?