Hello, During the sprint planning, we estimate the original time estimate at user story level. Sub-tasks are created in the due course of the sprint, where work is being logged. We expect that the remaining time originally given to the parent user story will be reduced whenever there are any worklog on its corresponding subtasks. This is not happening currently and Remaining time doesn't change (unless we estimate separately at the sub-tasks level).
Is there anyway that we can achieve this in Jira, without additionally estimating at the sub-tasks level? Thanks a lot!
Note: Though I found several posts already in the forum, couldn't come across a straightforward solution for this issue yet. Any suggestions would be helpful.
Best Regards, Tiju Thomas