Hi all,
I'm using auto-scheduler to create a high level project schedule, selecting epics only to schedule at this stage.
However i'm running into an issue which i haven't been able to find the cause of; Auto-scheduler keeps assigning my epics to past dates (-2months).
Steps i've taken to address this:
- removed any prescribed dates
- removed any sprints
- set epic one start date to today
no luck with this so far, thanks in advance.