I have a transition that automatically creates a subtask for each checked box of a multi-check field. However, I have encountered a couple of anomalies that I don't know how to resolve:
(1) the subtasks are created sometimes, but they are not linked to the parent issue
(2) the subtasks did not exist until a couple of days later; however, their creation date was correct
Using JIRA 6.0.2 with Script Runner 2.1.15.