I have a question. If we add some estimated task after starting a sprint (as scope change), it will be includeed?
Yes, scrum reports will show scope change.
Hello @Paulina Mijal
The Velocity Chart shows you the commitment at the moment the sprint is started, and the completed work at the moment the sprint ended. It is looking at all issues in the sprint at those two moments.
Changing the scope of work after the sprint starts will not affect the Committed metric for the sprint. All issues in the sprint will be considered for the Completed metric at the end of the sprint; it doesn't matter if the issue was added after the start of the sprint or if the scope for an issue already in the sprint changes.
https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-velocity-chart/