in Portfolio, I have 3 sub-tasks with dependency on one another, and have estimates visible and Target stat/end dates.... when i change end-date of one sub-task, can the dependent ones on this task change also accordingly automaticalli?
Hi @Sofia Foradoula
earlier I learned to auto-scheduling relies heavily on "Remaining Estimate" and it is capable of setting Due Dates/End Dates, if configured properly.
The following thread helped me a lot in understanding the mechanism better:https://community.atlassian.com/t5/Jira-Software-questions/Simple-dependency-chain-auto-scheduling-in-Advanced-Roadmaps/qaq-p/1638895
Sub-tasks were touched there also and I learned it is not possible for everything the users could think of.
Please also review the documentation:https://support.atlassian.com/jira-software-cloud/docs/configure-the-auto-scheduler-in-advanced-roadmaps/
Cheers,Daniel
It looks like you're new here. Sign in or register to get started.