Hi,
In some projects, we use the field "priority" to manage the issues that are blocked.
I want to know how many days an issue has the priority = "blocked".
Is there any way to get this information with jira or eazybi?
Thanks,
Luiza
@Luiza Silva
You can achieve it by using the "Time in Status" gadget on the Jira Dashboards. To do so, you have to create a filter or project and link it to your dashboard gadget.
Another option would be to look into some Marketplace plugins, such as https://marketplace.atlassian.com/apps/1211756/time-in-status?tab=overview&hosting=cloud
Regards!
Agreed with @Eugenio Onofre's solution of using "Time in Status" plugin.
@Luiza Silva, for your scenario of using a field to indicate the blocked status and to find the duration of the issue in that status, the aforesaid plugin is a boon. It has options to filter out issues based on a user/project/JQL filter/sprint/custom JQL. Once the required issues are filtered out using a JQL, we can view the different options like status duration/ duration between statuses/ reports based on assignee or group or count or date.
Hope this helps!
Thanks!
Hi @Luiza Silva ,
You can retrieve the duration an issue has been in a particular Priority in eazyBI with a calculated measure. The calculation would look at the transition dates in the Priority field for the particular value.
If you want to see the duration for individual issues, I recommend using the Issue dimension in report rows. First, to see only relevant issues, define a calculated measure that would return the number of transitions to the particular Priority. The formula could look similar to the one below:
([Measures].[Transitions to],[Transition Field].[Priority],[Priority].[Blocked])
You can add the measure to the report and then filter the report rows by it. Next, define a calculated measure to retrieve the duration with the particular Priority. See the suggested formula below:
IIf( -- issue still in the Priority? [Measures].[Issue priority] = 'Blocked', -- duration till now or resolution date DateDiffDays( TimestampToDate(( [Measures].[Transition to last timestamp], [Transition Field].[Priority], [Priority].[Blocked], [Time].CurrentHierarchy.DefaultMember )), CoalesceEmpty( [Issue].CurrentHierarchyMember.Get('Resolved at'), 'today' ) ), -- duration till transitioned out DateDiffDays( TimestampToDate(( [Measures].[Transition to last timestamp], [Transition Field].[Priority], [Priority].[Blocked], [Time].CurrentHierarchy.DefaultMember )), TimestampToDate(( [Measures].[Transition from last timestamp], [Transition Field].[Priority], [Priority].[Blocked], [Time].CurrentHierarchy.DefaultMember )) ))
The report then could look similar to the one below:
Please see the eazyBI documentation page for more details on defining calculated measures and filtering report rows.
Best,
Roberts // support@eazybi.com