I recently found that only some of the Issues on my board are making it to the next Sprint while other are put in the Backlog.
We have one Project that houses several Boards/Epics. The board where I complete/start Sprints houses a query where all epics associated with my App team and my Reporting team are put together.
When I complete the Sprint, I choose to move the open Issues to the next Sprint I have coming up (yet to start). Only the Issues from my App Team's Epics make it into the Sprint. The Reporting Team's Issues all go to the backlog.
Trying to determine if I am doing something wrong or if something has changed? How do I get ALL Open/Unresolved/In Progress Issues in my current Sprint to roll over to my next upcoming Sprint?