I have created several tasks. Now I would like to subsequently assign them to a parent task.
@Melanie Senn
You can use JQL to select all of the tasks you just created. Then use the Bulk Change tool to Move the tasks to Sub-Tasks. When you select the Subtask issue type as the destination, you will be asked to select the new parent issue. This process works for both Cloud and self-hosted.
-pjd
@Peter DeWitt Could you please share the JQL to move multiple tasks to subtasks?
@Melanie Senn Hi, You can follow the steps below.Go to Issues>Select Issues>Bulk Operation
Then Select Task type to Subtask and assign a parent for those tasks. Thanks!