Dear Team,
At one of our client implementations, we have got sync between Jira & Jira Align, with sprints syncing from Jira into Jira Align.
As per the recommended best practices, the scrum masters are not moving imcomplete stories from 1 sprint to another sprint, upon sprint closure, but moving them to backlog and pulling the incomplete stories from backlog into the future sprint.
This works fine as long as the incomplete story gets pulled in the future sprint.
However I have noticed that when the scrum masters move incomplete stories to backlog, & those stories are not pulled in a future sprint (for some reason - work getting de-prioritised etc.), the sprint value in Jira Align still persists to show as if the story is tagged to the previous sprint
Is this expected behaviour or once the incomplete story moves to backlog, upon sprint closure the story's sprint value in Jira Align should also change to unassigned backlog?
Thanks and Regards,
Mit Tolia