So Jira will not let you create a sub-task of a sub-task. So what is the recommendation to handle the following?
Epic
--task
----Subtask1A
------Subtask1B
------Subtask2B
----Subtask2A
I want to be able to track the "B" tasks which are under Subtask1A.
with due dates, comment essentially all functionality of jira ticket issue A.
thanks