Hi,
We have a custom workflow in jira : ToDo->In progress->Dev Blocked->QA->QA blocked->UAT testing->Uat blocked->UAT Validated->Done.
During the sprint changeover the tickets that are in blocked state are not counted towards the carry forward story points. these blocked tickets do carry forward but their story points are not counted. So it does not show a correct picture of the story points carry forward in either Burndown or Burnup charts.
Is there a way to get the correct amount of SP reported. AT present i am able to query on it. Is it a possibility in Jira server to modify the way it reports or any other tool that can be customized to this level?
Thanks,
Amit