Hi all,
Setting up my team to use the advanced roadmapping tool for planning and execution. Quick question regarding how pointed epics are allocated into sprints. Currently the work seems to be front loaded into the first available sprint (see screenshot below), however it would be more beneficial for planning if the points were evenly distributed over the projected sprints due to siloing and specialization.
Example: Epic is 48 points, each sprint is 30 points, ideally I'd like each sprint to be loaded up to 16 points each. However current loading is 30 points in the first sprint and 18 points in the second sprint.
I know this could potentially be done by dividing teams up into more granualar subsets, however that would introduce more overhead on the sprint management side of things.
Thanks in advance!