Hi Admins!
I pulled a Cumulative Flow Diagram for our last sprint (I adjusted the dates to be in line with my sprint dates). (2 August 2021 to 18 August 2021)
If I look at the diagram - the number of issues does not seem correct.
The diagram reflects 0 - 150 Dev Done,
150 - 200 (i.e total of 50) In Progress
200 - 400 (i.e 200) To Do.
See attached for diagram
The correct totals as per my sprint report should be as per the below.
Grand Total 133
| DEV DONE | 73 |
| DONE | 7 |
| IN PROGRESS | 13 |
| TESTING | 5 |
| TO DO | 35 |
I am reading the diagram incorrectly? The dates at the bottom of the diagram is correct.