Hi!
We have Jira Structure plug in and we want to use Gantt Chart to track the progress of the project and see the whole picture. However, I cann't find the answer to my question.
What we do: we have a project which has some Jira tickets. Every ticket represents the specific task to do for the team. Every task has an estimated time.
Example: Let's say there is a task IMP-1 "Create a power point presentation" and we expect to spend 10 hours to complete the task. The work started, we logged in out time spent for this task and in total it gave us 6 hours instead of 10 hours. We did it faster than expected.
What we want to see: We want to see the bar (or something like this) on the Gantt chart which shows the estimated time for this task (10 hours) and which also shows the real time spent on this task (6 hours).
Is there any way to track this and see it on Gantt chart somehow? If yes, how we can do it?
Thank you!