Hi there!
PS- I have all the right permissions, as I have done this many times, and I just messed up on the sequence of actions, by beginning a new sprint (clicking start sprint) on the same project before closing the current one. This is not a caching/permission issue.
I forgot to complete my sprint, before starting a new one and now the 'complete sprint' button is gone, and it has a shadow, with the hover stating 'you can only complete 1 sprint at a time'
I adjusted the swim lanes query to only show one sprint, but since I started the other, it displays under 'everything else'
What can I do to complete my sprint now, so that the dialog box can appear for everything to go over to the 'new' sprint.
If I go to reports, and pick a chart like the velocity chart, the sprint I forgot to close in the right sequence, doesn't show up, so it seems to still be in an open state, but I can't seem to complete it.
I would really appreciate the help
Thanks