Our Scrum Software type project only uses a single shared workflow.
The resolution needs to be set manually during the Fix transition.
As a project administrator, how can you achieve this?
A. Add the Resolution field to all project screens.
B. Check the Set Resolution option on the target status in your board configuration.
C. Request a post-function to be configured for the Fix transition.
D. Request a screen with the Resolution field to be associated with the Fix transition.
E. Add the Resolution field to the screen associated with the Fix transition.
As per me answer will be D. As resolution needs set manually during the Fix transition.
Please let me know if its correct or not!