Hi,
I am a civil engineer trying to adapt JIRA for a construction project. It's a project of 398 identical houses divided by blocks of 28 houses, 32 houses, 27 houses, etc. With that in mind, someone gave me the idea to transform the blocks into EPICS and the houses into STORY issues. In each STORY (house), I will have the sub-tasks needed to complete the construction of the house in its totality (100%), and the % value of each sub-task it's based on the amount of money that they represent in the certificate. For example, concrete foundation 5%, brick wall 2%, etc. The % of the progress of a STORY (house) is the number of sub-tasks done divided by the total number of sub-tasks, meaning that all sub-tasks have the same value. Is it possible to give different % values to the sub-tasks?