Hi, I am a civil engineer, and I wondered if Jira can be used for construction projects with massive repetition of tasks. It’s a project of 398 identical houses divided by blocks, for example, 28 houses in block 539, 32 houses in block 518, 27 houses in block 485, etc. All the houses are the same, with the same tasks and sub-tasks. What is the best way to use Jira? The best idea that I had was to create issues like FOUNDATION as Tasks and issues like CONCRETE IN FOUNDATION as subtasks connected to the issue FOUNDATION, after that I thought about cloning the issue FOUNDATION for each house, that are the EPICS of the project, and finally, each block is a different project. But that is not very productive. Can anyone help me?