I am leveraging advanced roadmaps across 10 different jira projects so that I can visualize and manage cross-team dependencies. Each project = 1 team.
1. To get a Team associated to a Jira issue, I have to publish an edit to Advanced Roadmaps.
This spams the team with email notifications (they have a lot of tickets in their respective projects). Is there any workaround to not do this? I tried to bulk edit within Jira but looks like this needs to be done from Advanced Roadmaps.
2. Assuming every issue in a Jira project needs to be associated with its respective team, is there any sort of clean automated way to ensure new Jira issues are tied to the team? Or is this something we need to manually reconcile on a continuous basis?