Hello,
I am new Scrum master and new in Jira also
I am trying to make a good prediction of tasks during a Sprint for my team and I want to use the old sprint to make a realistic prediction.
My question is if the calculation the velocity chart depending on the Story points number why jira doesn't cosider sub-tasks in the equations and put the Story (task type) to equal to 0
Isn't that make the velocity chart not so accurate?