how can i change the issue types in a project without affecting the other projects? for example if i want to delete all the epics in the structure of a project and have just stories and tasks ( or anything similar to this example ) . I know I read how to do it somewhere long ago but I forgot where
You need to separate out the "issue type schemes". Create a new issue type scheme (I tend to copy the existing one and modify it), remove Epics from it and then apply it to the project that doesn't need epics.
thank you !