I currently have one set of product teams that start their sprints one day earlier than everyone else. With that, it becomes challenging to determine when to start and end my program increments. For example:
PI1 ends on a Monday because that one set of teams starts their sprints on Tuesdays
PI2 starts on Tuesday
My teams that start on Wednesday are not affected for PI2 but those same teams have this one day to reconcile (last day of sprint/PI1 on Tuesday).
I know the simple answer is to align all teams on the same sprint cadence. Until then, do I leave PI1 in progress and also start PI2? Will that have negative repercussions? As long as the dates don't overlap in JA, I believe the last day of work will be captured in PI1.