I have some end to start dependencies in BigPicture. Sometimes the target item is scheduled before the end of the source item. Meaning we can not meet the end to start dependency. This can happen when a target item has a hard start date and the source item has been delayed.
Is there any possibility to highlight items in such a situation in BigPicture? I'm looking for a view similar to overdue tasks in the info bar but for dependency issues like described above.
It would also be nice to show those items in a different color on the gantt like we have for critical path and overdue.