I read where if a team exceed its capacity (velocity) for a sprint the issue is only partially scheduled. Does this mean that Portfolio only schedules to the teams capacity and the rest is unscheduled? I can see where this makes sense for future sprints, but the active sprint means the team has committed to completing this work. Can you clarify how this works and the rationale for it. It may just be that this is the most conservative view, but I want to make sure I understand what my plan is representing.