I've noted there's an (extremely annoying) existing issue that 'Done' stories wont show in the plan regardless of the scope or the filter used - can someone tell me if they've worked around this - so I'm curious if anyone gets the progress meter correctly showing Done issues as a percentage of the total?
See screen shot for example, where there's 6 stories linked to the epic and one is done.

Our problem is that our roadmap is not tracking progress as anything that's done or closed just disappears and doesn't remain for the x days as specified in scope.